OEG-CML-002 · NOT_ESTABLISHED
The 800VDC / SST architecture has been replicated by multiple independent entities.
The public record supports a single operator-reported instance, not replication across independent operators or sites.
- Case
- CML-PDRE-001 · 800V DC Data Center Power Architecture
- Claim
- CML-PDRE-001.MULTI_ENTITY_REPLICATION
- Current state
- NOT_ESTABLISHED
- Evidence cut-off
- 2026-09-20T10:46:47Z
- Last reviewed
- 2026-10-05
What is established
- A single named operator reported one materially relevant field deployment.
What is not established
- A second independently attributable deployment
- Multi-operator replication
- Repeat procurement or industry adoption
What would change this
A public record for another attributable operator or independently controlled site showing a materially comparable deployed architecture and operating status.
Qualifying boundary
Examples that may qualify
- Named operator commissioning record
- Regulatory or grid-connection record
- Independent case study identifying operator, site, architecture, and date
Examples that do not qualify
- Multiple articles about the same site
- Planned projects without commissioning
- Vendor pipeline totals without named deployments
Append-only
Public change log
Accepted evidence may result in a state change, no state change, or scope clarification. Earlier entries remain visible.
- 2026-10-05 · GAP_OPENED
Initial open evidence gap published under Open Evidence Gap Protocol v0.1.
StructEvidence