OEG-CML-002 · NOT_ESTABLISHED

The 800VDC / SST architecture has been replicated by multiple independent entities.

The public record supports a single operator-reported instance, not replication across independent operators or sites.

Case
CML-PDRE-001 · 800V DC Data Center Power Architecture
Claim
CML-PDRE-001.MULTI_ENTITY_REPLICATION
Current state
NOT_ESTABLISHED
Evidence cut-off
2026-09-20T10:46:47Z
Last reviewed
2026-10-05

What is established

  • A single named operator reported one materially relevant field deployment.

What is not established

  • A second independently attributable deployment
  • Multi-operator replication
  • Repeat procurement or industry adoption

What would change this

A public record for another attributable operator or independently controlled site showing a materially comparable deployed architecture and operating status.

Qualifying boundary

Examples that may qualify

  • Named operator commissioning record
  • Regulatory or grid-connection record
  • Independent case study identifying operator, site, architecture, and date

Examples that do not qualify

  • Multiple articles about the same site
  • Planned projects without commissioning
  • Vendor pipeline totals without named deployments

Challenge this gap

Append-only

Public change log

Accepted evidence may result in a state change, no state change, or scope clarification. Earlier entries remain visible.

  1. 2026-10-05 · GAP_OPENED

    Initial open evidence gap published under Open Evidence Gap Protocol v0.1.

    StructEvidence